Used in: Stock Planner
MRP uses expedite and reschedule messages to show when open supply no longer matches when it's needed.
Core Planning Concept
MRP systems calculate projected inventory balances across future time buckets.
As projected supply and demand conditions change over time, some open supply orders will no longer arrive when they're needed.
Exception messages are generated when the MRP calculation finds that open supply no longer matches what the plan needs, for example an order that should be brought in, pushed out or cancelled.
Examples may include:
- Projected shortages
- Inventory projected below safety stock
- Supply arriving later than required
- Supply arriving significantly earlier than required
- Excess projected inventory
Expedite Logic
An expedite recommendation is triggered when projected inventory falls below safety stock before an existing open supply order arrives.
In simple terms:
- Projected inventory drops below safety stock
- An open supply order is due in a later period
- MRP recommends bringing that order forward
Reschedule Logic
A reschedule-out recommendation is triggered when an open supply order is due before it's needed.
In simple terms:
- Projected inventory stays above safety stock without that order
- An open supply order is due in an earlier period than needed
- MRP recommends moving that order out to the period when projected inventory would otherwise drop below safety stock
Noise
Expedite and reschedule messages can create a lot of noise. Depending on your time buckets, MRP may recommend moving an open order by just a day. That's logically correct, but it isn't worth acting on, and dozens of small messages can hide the ones that matter. Find the sweet spot: set your time buckets or a minimum change so that only meaningful moves show up.
Relationship to MRP
Expedite and reschedule recommendations are outputs of the MRP calculation.
The planning system first calculates projected inventory balances over time, then evaluates whether existing supply timing still supports planning objectives.
The timing of supply is often just as important as the quantity of supply.
A company may have sufficient total inventory overall, but still experience shortages if supply arrives too late.
Important Operational Consideration
Frequent expedite activity may indicate underlying planning issues such as:
- Poor forecast accuracy
- Incorrect lead times
- Supply variability
- Inventory inaccuracies
- Capacity constraints
Many organizations attempt to reduce unnecessary expedite activity because expediting often increases operational cost, planning instability, and supply chain variability.
See also: Supply order, Planned order, Past-due